$720K less in annual GTM technology spend.

I consolidated overlapping tools and renegotiated contracts across a $3M global technology portfolio.

$720K

Documented result

GTM systems spend reduced through tool consolidation and contract renegotiation.

$720Kannual GTM systems spend reducedHow to read this result +

Annual expense reduction at UiPath through negotiation, consolidation, and license right-sizing across a $3M portfolio.

UiPath / GTM technologyThe decision order
  1. 01 / MapCapabilities & usage

    What do teams need? Where do tools overlap?

  2. 02 / CheckDependencies & risk

    What must keep working? What does a change affect?

  3. 03 / DecideConsolidate & negotiate

    Work with Procurement and InfoSec on the change.

Check what teams need before changing what they use.

The decision

Start with what the team needs to do.

Two tools can look redundant while supporting different workflows. I evaluated capability overlap, usage, and integration dependencies before deciding what could move or go.

The tradeoffA lower contract total is not useful if the change leaves teams without a capability they depend on. Cost reduction had to preserve that coverage.

The scope

A $3M technology portfolio.

I managed a $3M global GTM technology portfolio. The challenge was to reduce cost while keeping the tools and integrations revenue teams needed.

I worked with Procurement and InfoSec to consolidate tools and renegotiate contracts, checking each decision against security requirements and the teams using the software.

What I did.

  1. Treat coverage as a requirement

    The scope was to reduce spend without stripping away capabilities the revenue organization relied on.

  2. Find overlap before cutting

    The portfolio was evaluated for redundant capability, real usage, governance risk, and integration dependency.

  3. Work with Procurement and InfoSec

    Procurement and InfoSec helped evaluate the contracts, security requirements, and dependencies.